Another leaking was detected which hindered us from conducting the activity. Repair is currently in progress. Releasing of water from the ITWD Water Treatment Plant reservoir to Ipil Service area will continue as soon as the repair is completed. Thank you.
-PUBLIC ADVISORY-
To all ITWD concessionaires, the ITWD will be conducting a Preventive Maintenance Cleaning activity on January 15, 2024 for Touwa Well 3 affecting Ipil Service Area. There will be LOW PRESSURE TO NO WATER especially to elevated areas. The maintenance will last as soon as the work is completely done. We are very sorry for continue reading : -PUBLIC ADVISORY-
ONGOING REPAIR OF 200mm TRANSMISSION LINE
Location: Domandan, Ipil, Zamboanga Sibugay Today, January 9, 2023 This is to inform the public that the temporary released of water from the ITWD Water Treatment Plant Reservoir in Domandan yesterday was interrupted due to the damage in the 200mm transmission line. The damage was caused by high pressure of water coming from the reservoir. continue reading : ONGOING REPAIR OF 200mm TRANSMISSION LINE
– PAHIBALO ALANG SA TANAN –
Tungod sa atong nasinatiang kainit sa panahon nga nagresulta sa kakulangon sa supply sa tubig, gipahibalo ang tanang miyembro konsumante sa Ipil-Titay Water District nga karong adlawa, ato ng TEMPORARYONG ipasulod sa atong linya ang tubig nga gikan sa atong bag-o nga water source didto sa Domandan para ma-utilize na sa publiko while continue reading : – PAHIBALO ALANG SA TANAN –
-PUBLIC ADVISORY-
To all ITWD concessionaires, the water interruption in some parts of Ipil and Titay is caused by power curtailment at Titay pumping station (single phased supply of power) from 11:33PM last night until 6:54AM this morning. We are very sorry for the inconvenience. Rest assured that we will do our best to bring back normal continue reading : -PUBLIC ADVISORY-
-PUBLIC ADVISORY-
To all ITWD concessionaires, the ITWD will be conducting a Preventive Maintenance Cleaning activity on January 8, 2024 for Samporna Well affecting some parts of Tiayon & Don Andres, Veterans Village, Top Mars Phase 1, 2 & 5. There will be LOW PRESSURE TO NO WATER especially to elevated areas. The maintenance will last as continue reading : -PUBLIC ADVISORY-
Design and Build Contract for ITWD Water Supply System Improvement Project (Update)
– PROJECT UPDATE – Project name: Design and Build Contract for Ipil-Titay Water District Water Supply System Improvement Project ✓ On-going Rehabilitation of 50mm Lateral Pipelines at Top Mars, Phase 1, Veterans, Ipil, ZSP
Design and Build Contract for ITWD Water Supply System Improvement Project (Update)
– PROJECT UPDATE – Project name: Design and Build Contract for Ipil-Titay Water District Water Supply System Improvement Project ✓ On-going Rehabilitation of Main Pipelines at Bangkerohan, Ipil, ZSP
EL NIÑO PHENOMENON
– EL NIÑO PHENOMENON – As we head into 2024,rising temperature is expected leading to prolonged dry spells and drought. This can result to reduced water supply. Currently, the adverse effects of El Niño have been felt by some of our concessionaires in Ipil and Titay. According to the Philippine Atmospheric, Geophysical and Astronomical Services continue reading : EL NIÑO PHENOMENON
Design and Build Contract for ITWD Water Supply System Improvement Project
– PROJECT UPDATE – Project name: Design and Build Contract for Ipil-Titay Water District Water Supply System Improvement Project Location: Kitabog, Titay, Zamboanga Sibugay ✓ Construction of 200 cubic meter ground reservoir ✓ Interconnection of the 200 cubic meter reservoir to the Distribution pipelines